The stays are in a single plane with a semi harp arrangement and are anchored every 7 m in the deck. The 80 m high pylons.

  • Location
    Kota, Rajastan
  • Client
    Hyundai Engineering & Construction
  • Awarded
    2012
  • Status
    Completed
The project

Supply and Installation of Stay Cable Work, PT Work & Construction and Operation of Form Traveller Work

The stay cables are composed of individually sheathed strands having a triple protection, galvanization, wax filling and individual polyethylene sheet. The external cable duct has helicoids in order to eliminate rain and wind induced vibrations.

  • 1100 m
    Length of the Bridge
  • 30 m
    Width
  • 125 m
    Pylons

Contact us

You have a question about our solutions or you already have a project in mind? Please fill out the form below and our teams will get back to you shortly.